What is moving through the county
Del Webb Sunchase has a new piece of its next phase in Manatee County’s paperwork: a final-plat application covering 161 single-family homes in Phase II-A and Phase II-B.
The filing appears in the county’s November 9 weekly development list, which covers November 2–8. It identifies the property at 14450 Sundrop Court in Parrish and lists the review as administrative.
The county description says the earlier combined plan for phases II-A, II-B and II-C was approved under PLN2410-0019. This application, PLN2610-0155, covers only the first two. Phase II-C will be platted separately later.
Access is described through Sunchase Phase I, with emergency connections to existing Crosswind Ranch. That last word matters: an emergency connection is not a promise of a new everyday shortcut between neighborhoods.
The list documents an application. It does not give a final approval date, a sales-release date or a move-in schedule for these 161 homes.[1]
The amenity calendar is a separate story
Sunchase is a 55+ community, and Del Webb’s current page still marks its amenities as in progress. The Solara Clubhouse update points toward 2027; the East Amenity Campus is also listed as coming soon.
The advertised lineup includes shaded pickleball courts, a clubhouse and fitness center, resort and resistance pools, and Beachwood Tap Bar & Grille. Treat that as the planned lifestyle package, not a list of facilities you can assume are all operating today.
There are two opportunities to get a closer look. The builder lists a Friendsgiving potluck for homeowners and future residents November 17, from 5:30 to 7:30 p.m., and an amenity preview and walk-through December 14 at 3 p.m. Both have RSVP links on its community page.
The sales center address is 9114 Sunset Haven Terrace, separate from the property address on the county filing.[2][1]
My take for buyers
I’d separate three questions before falling in love with a floor plan: Which homesite can I buy? When can that particular home be delivered? Which amenities will be ready when I arrive?
A phase count answers none of those by itself. Ask for a dated homesite map and a written completion estimate tied to the home you are considering. Then compare that with the amenity schedule.
For a buyer planning a move six months out, those dates can matter as much as the kitchen selections. The useful update here is specific: Sunchase has a defined next plat, while its larger amenity buildout has its own timeline.[1][2]
Sources & verification date
- Manatee County · November 9 weekly development project list, page 3 ↗
Checked 2026-11-10 · Source first published 2026-11-09 - Del Webb · Sunchase community and event announcements ↗
Checked 2026-11-10
Something changed, or something we should correct? Let Trenton know. Read our editorial standards.